July, 2011. SINOPOWER supplied 57 units to Japan in 5 weeks.
SINOPOWER supplied 57 transformers in 6 weeks for Japan as part of a fast-track power solution following the tragic Tohoku-Chihou-Taiheiyo-Oki Earthquake and associated tsunami on March 11, 2011 that caused damage to the nation's energy grid. The 57 transformers include 3 units of 66kV, 100MVA series, 33kV/11kV aux transformers, and 33kV 4MVA pad mounted transformer. Total lead time from ordering to delivering took only 5 weeks. By July 3, all the transformers are ready to be energized in Japan with SINOPOWER's commissioning supervision and inspection.